Rail Bridge Dromantine Hill Newry Co Down BT35 6TG

Drumantine, Newry, Mourne and Down, Northern Ireland

The record

Designation
Record only (not listed)
Grade
Record Only
Type
Bridge
Date of construction
1840 - 1859
Address
Rail Bridge Dromantine Hill Newry Co Down BT35 6TG
Townland
Drumantine
Council
Newry, Mourne and Down
Country
Northern Ireland
Coordinates
54.26511, -6.36344
Date of survey
03 August 2023
HB reference
HB16/21/047

Slide toward Today to fade the historical sheet and see the modern map underneath.

David Rumsey Map Collection, Stanford Libraries

Shown on 4 historical map sheets, the earliest the 1838 "Ireland, north sheet." (David Rumsey Map Collection, Stanford Libraries).

Get directions ↗

This record in the Department's Historic Buildings Record ↗

The Department's description

Single span, skewed, segmental-arched rail bridge over road carrying Belfast-Dublin railway line built 1850-1, located at W end of Drumantine Hill, approximately 7.5miles N of Newry, Co Down (IHR 00062:152:00).

West face: Spandrals in squared random-coursed rock-faced stone with large cut-stone rock-faced voussoirs to arch. Sloping wing-walls to each side. Wing-wall on left side has concrete coping and cement-rendered band below, wall abutted at NW end by low stone pier. Concrete coping to wing-wall on right side.
Cut stone string course above segmental arch; cement-rendered parapet with replacement concrete coping, topped by plain tubular metal railings.

East face: Design and detailing as per W face.

Beneath arch, coursed rock-faced granite to pier walls; stone string course below a row of skewed kneeler stones; brickwork aligned along kneeler stones; red brick soffit in English Bond (alternate header & stretcher coursing).

Materials:
Rock-faced granite, brick soffit, replacement concrete coping, modern metal railings.
(Note – bridge deck not seen at time of survey)

Setting:
Located on Drumantine Hill in a rural location, in close proximity to several other bridges – Gambles Railway bridge (HB16/21/076) to the immediate S, and Gambles Road Bridge (HB16/21/075) to the NW.

The current bridge was built in 1850-1 to carry the Dublin and Belfast Junction Railway over a pre-existing road in Drumantine townland, and responsibility for its design, and the design of other bridges on this line, fell to noted railway engineer Sir John Macneill, and his assistant James Barton (contributions may have been made by other resident engineers). The bridge is first shown, captioned ‘Drumantine Bridge’ on the 2nd edition of 1860, but is not captioned on later editions.

In 1845 an Act incorporated the Dublin & Belfast Junction Railway to build a line between the termini of existing lines at Drogheda (Dublin & Drogheda Railway) and Portadown (Ulster Railway) passing to the W of Newry, and connecting Dublin with Belfast. Work on the line commenced at Drogheda and had reached Killeen, to the S of Newry by July 1850. A line was driven south from Portadown to Goraghwood between 1850 and 1851, and the current bridge was built during this year. Although various contractors were employed on the line between Drogheda and Portadown, which was divided into six separate contracts, William Dargan was the contractor for the Portadown to Goraghwood section (No 6) of the railway.

Carlow-born William Dargan (1799-1867), was a celebrated building contractor and railway entrepreneur, a pupil of Thomas Telford and responsible for numerous roads, railways, canals and docks in Ireland and also in Britain. Dargan won the contract to build Ireland’s first railway line, the Dublin and Kingstown, in 1834 and his successful completion of this line enabled him to win a substantial share of Irish railway construction contracts in the 1840s and 50s, including parts of the Dublin & Belfast Junction Railway.

The engineer-in-chief employed by the Dublin and Belfast Junction Railway was Louth-born Sir John Macneill, a former pupil of Thomas Telford who worked in England and Scotland until the late 1830s when he was recruited by the Irish Railway commissioners to survey and lay out the railway system in the north of Ireland. Macneill was afterwards employed as chief engineer to numerous Irish railways, receiving a knighthood following his work on the Dublin to Drogheda line. In the north, Macneill was engineer to Dundalk & Enniskilllen Railway, the Belfast & County Down Railway, the Downpatrick, Dundrum & Newcastle Railway and the Belfast Central Railway. Macneill was professor of Civil Engineering at Trinity College, Dublin (1842-52) and also designed a bridge over the Royal Canal, which was the first iron lattice bridge in the UK. He was responsible for numerous railway bridges and viaducts, including several timber viaducts with masonry abutments for the Dublin & Drogheda Railway. Macneill also designed the Craigmore Viaduct, the Egyptian Arch and the Boyne viaduct which were completed as part of the works on the Dublin and Belfast Junction line.

The District Engineer for the Dublin and Belfast Junction Railway was James Barton (1826-1913) (several resident engineers were also employed). Barton was employed as a deputy to Macneill after Macneill’s commitments elsewhere, particularly on the Great Southern & Western Railway from Dublin to Cork, had resulted in neglect of his duties towards the Dublin and Belfast Junction Railway Board. Barton, had been a student of Macneill’s at Trinity, and made important contributions to the design of the Boyne viaduct while working with Macneill, along with resident engineers Alexander Schaw and William Powell (the relative contributions to the design of the various engineers who worked on it were the subject of some controversy in the years after the Boyne viaduct opened). Barton later became a consultant for numerous railway companies, mostly in the north. His obituary named him ‘one of the pioneers of Irish Railway construction and development’. A resident engineer, William Powell, exhibited ‘A ground plan of the ‘Dublin and Belfast Junction Railway’ with elevations of the principal bridges, viaducts &c at the Royal Hibernian Academy in 1852.

In August 1850, Sir John Macneill reported to the Dublin and Belfast Junction Railway Company on progress with the 16 miles of line from Goraghwood to Portadown under contract to Dargan, ‘The bridges are in a forward state; five of them are very nearly completed with the exception of the parapet, and three others are far advanced’. A year later, in August 1851, Macneill reported that all the bridges (except one over the Cusher River) between Craigmore and Portadown had now been completed. The section of railway between Mullaghglass (to the S of Goraghwood) and Portadown opened to the public on 6th January 1852, but the line from Drogheda to Portadown was not opened until June 1852 after completion of the Craigmore viaduct and it was not until June 1853 that the first train with passengers crossed the Boyne viaduct, thus completing the line between Dublin and Belfast (the Boyne viaduct was initially opened with a temporary wooden structure carrying trains, the permanent structure being completed in April 1855).

Dublin and Belfast Junction Railway became amalgamated into the Great Northern Railway (Ireland) in 1876 and was ultimately taken over by Northern Ireland Railways, a publicly owned train operator, in the 1960s.

References:
Primary Sources:
1. PRONI OS/6/3/40/1 First edition Six Inch OS map (1834)
2. London Evening Standard, 5th July 1850
3. Dublin Evening Packet, 29th August 1850
4. Freeman’s Journal, 29th August 1851
5. Newry Telegraph, 6th January 1852
6. Evening Freeman, 9th May 1853
7. Newry Examiner, 7th December 1853
8. PRONI OS/6/3/40/2 Second edition Six Inch OS map (1860)
9. PRONI OS/6/3/40/3 Third edition Six Inch OS map (1903)
10. PRONI OS/6/3/40/4 Fourth edition Six Inch OS map (1903-18)

Secondary Sources:

11. Dictionary of Irish Architects: www.dia.ie
12. Dictionary of Irish National Biography: www.dib.ie
13. Geraghty, P.J. (2017) “The Dublin and Belfast Junction Railway: The Great Link Uniting Dublin and Belfast” Journal of the County Louth Archaeological and Historic Society, Vol 29, No1, pp.96-136
14. Hamond, F – scheduling information held by Historic Environment Division
15. McCutcheon, W A (1980) ‘The Industrial Archaeology of Northern Ireland’ Belfast: HMSO

Not listed

Not listed

Single span, skewed, segmental-arched rail bridge over road carrying Belfast-Dublin railway line built 1850-51, located at W end of Drumantine Hill, approximately 7.5miles N of Newry, Co Down. Despite the skewed brick soffit, this bridge is of a common type and has insufficient special interest to meet the criteria for listing.

Nearby in the register

Other entries of the same register within about three miles of this one, by straight line.

Department for Communities, Historic Environment Division, Historic Buildings Record. Contains public sector information licensed under the Open Government Licence v3.0. Department for Communities, Historic Environment Division · Open Government Licence v3.0
See your own family's places on a living map